Substation Scout

Every tracked change

4 changes recorded since change tracking began on August 27, 2026.

What is and is not in this list

This is the complete set of differences the pipeline has observed between two published queue snapshots. Each row is a change to a filing: a status the ISO restated, a request that moved to withdrawn or cancelled, or a nameplate figure the developer revised.

The first scan on August 27, 2026 stored a baseline for 3,054 requests. Those are first observations, not observed movement — there was no earlier snapshot to compare them to, so they are excluded here rather than inflating the count.

MW figures are nameplate as filed. A request leaving the queue does not mean capacity is obtainable at that location; verify with the ISO before relying on any row.

4total changes
3terminal status
1status change
1comparison runs
DetectedISOChangeRequest MW as filedStatus was → now
2026-08-31 PJM Terminal status Southern Ocean Waretown Solar
AG1-189 · Ocean County, NJ
5.1 Engineering and Procurement Pending Termination
2026-08-31 PJM Status change Walnut Solar I
AC1-065 · King and Queen County, VA
n/a Under Construction Partially in Service - Under Construction
2026-08-31 PJM Terminal status Dequine - Eugene 345 kV
C01-2193 · Fountain County, IN
250 Active Withdrawn
2026-08-31 PJM Terminal status Dequine - Eugene 345 kV
C01-2192 · Fountain County, IN
240.5 Active Withdrawn

Requests link to their project page where one exists. Some ERCOT records appear only on the ISO's exit sheets and have no queue page of their own.