Rosenix Storage (29INR0213) is listed in the ERCOT interconnection queue as a 258.3 MW battery project in Mitchell County, TX. The filing names Cattleman (#) – Gasconades (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 20, 2030. It records the screening study as complete on October 14, 2026.
| Queue ID | 29INR0213 |
|---|---|
| Project name | Rosenix Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Cattleman (#) – Gasconades (#) |
| Point of interconnection | Cattleman (#10053) – Gasconades (#76030) |
| County | Mitchell |
| State | TX |
| Voltage | Not reported |
| Capacity | 258.3 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-04-20 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Cattleman (#) – Gasconades (#) substation: 2 requests in the ERCOT queue, 2 active totaling 759.9 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 29INR0212 | Rosenix Solar | 501.6 | Solar | SS Completed, FIS Started, No IA |
Mitchell, TX: 19 requests in the ERCOT queue, 17 active totaling 7,498.1 MW.
Tracked changes
2 changes observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-11-09 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-10-05 | Capacity revised | +8.3 | SS Started, FIS Started, No IA → SS Started, FIS Started, No IA |
Additional filed fields
| Interconnecting entity | Rosenix Solar, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2026-10-14 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.