BPA queue ID G0684

Queue IDG0684
Project nameNot reported
Status (as published)STUDY COMPLETED
SubstationWautoma Substation
Point of interconnectionWautoma 500 kV Substation
CountyBenton
StateWA
Voltage500 kV
Capacity470 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2024-10-01
Source datasetbpa-generation

Tracked changes

1 change observed between weekly snapshots of the BPA queue since BPA tracking began on September 22, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a STUDY → STUDY COMPLETED

Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiWautoma 500 kV Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total705
Max Summer Mw470
Max Winter Mw470
ClusterTransition Late Stage
Reason Not Completed.
CommentsMaximum instantaneous injection of the project (generation + storage) will not exceed 470 MW at POI