Trail Ranch Solar 1
ERCOT queue ID 29INR0139
| Queue ID | 29INR0139 |
|---|---|
| Project name | Trail Ranch Solar 1 |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap # Red Creek - # AMOS Creek |
| Point of interconnection | Tap 345KV #6444 Red Creek - #7077 AMOS Creek |
| County | Concho |
| State | TX |
| Voltage | 345 kV |
| Capacity | 302.2 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2029-12-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Aurora Solar LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 46041 |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.