Huisache BESS

ERCOT queue ID 24INR0376

Huisache BESS (24INR0376) is listed in the ERCOT interconnection queue as a 100.7 MW battery project in Wilson County, TX. The filing names Tapping the Elm Creek to Shaula circuit 1 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of June 30, 2029. It records the screening study as complete on November 1, 2022, the full interconnection study as approved on August 25, 2025 and the interconnection agreement as signed on August 12, 2025.

Queue ID24INR0376
Project nameHuisache BESS
Status (as published)SS Completed, FIS Completed, IA
SubstationTapping the Elm Creek to Shaula circuit 1
Point of interconnectionTapping the Elm Creek to Shaula circuit 1
CountyWilson
StateTX
VoltageNot reported
Capacity100.7 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-06-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tapping the Elm Creek to Shaula circuit 1 substation: 2 requests in the ERCOT queue, 2 active totaling 226.3 MW.

Queue IDProjectMWResourceStatus
24INR0160Huisache Solar125.6SolarSS Completed, FIS Completed, IA

Wilson, TX: 18 requests in the ERCOT queue, 15 active totaling 3,532.8 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-11-09 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting entityHuisache Solar, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2025-08-12
Screening study complete2022-11-01
Full interconnection study approved2025-08-25

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first