M-Bar Solar I

ERCOT queue ID 27INR0421

Queue ID27INR0421
Project nameM-Bar Solar I
Status (as published)SS Completed, FIS Completed, No IA
SubstationHolt Switch Substation
Point of interconnection1141 Holt Switch Substation 138kV
CountyEctor
StateTX
Voltage138 kV
Capacity30.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-09-18
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Status change n/a SS Completed, FIS Started, No IA → SS Completed, FIS Completed, No IA

Full change log →

Additional filed fields

Interconnecting EntityM-Bar Energy I, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45733
Fis Approved46259
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.