Eagle Claw Energy Center

ERCOT queue ID 27INR0085

Queue ID27INR0085
Project nameEagle Claw Energy Center
Status (as published)SS Completed, FIS Started, IA
SubstationSingleton (Bus #) - Zenith (Bus #) Circuit #99
Point of interconnectionSingleton (Bus #44645) - Zenith (Bus #44900) Circuit #99 345 kV
CountyGrimes
StateTX
Voltage345 kV
Capacity204.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-03-31
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Completed, IA → SS Completed, FIS Started, IA

Full change log →

Additional filed fields

Interconnecting EntityEagle Claw Energy Center, LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Ia Signed45915
Screening Study Complete45301
Air PermitNot Required