ERCOT queue ID 27INR0085

Queue ID27INR0085
Project nameEagle Claw Energy Center
Status (as published)SS Completed, FIS Completed, IA
Substation30., -95. - Singleton (Bus #) - Zenith (Bus #) Circuit #98 Line
Point of interconnection30.615932, -95.962023 - Singleton (Bus #44645) - Zenith (Bus #44900) Circuit #98 345 kV Line
CountyGrimes
StateTX
Voltage345 kV
Capacity204.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-03-31
Source datasetlarge

Additional filed fields

Interconnecting EntityEagle Claw Energy Center, LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Ia Signed45915
Screening Study Complete45301
Fis Approved45595
Air PermitNot Required