Honey Creek Solar (AF2-078) is listed in the PJM interconnection queue as a 120 MW hybrid project in White County, IN. The filing names Reynolds-Olive #1 as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of December 31, 2027.

Queue IDAF2-078
Project nameHoney Creek Solar
Status (as published)Under Construction
SubstationReynolds-Olive #1
Point of interconnectionReynolds-Olive #1 345 kV
CountyWhite
StateIN
Voltage345 kV
Capacity120 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalized for filtering)
Target commercial operation2027-12-31
Source datasetserial

Same substation and county

Reynolds-Olive #1 substation: 3 requests in the PJM queue, 3 active totaling 334 MW.

Queue IDProjectMWResourceStatus
AF2-132Mammoth Central Energy Center180SolarPartially in Service - Under Construction
AF1-207Hoosier Line Solar34SolarUnder Construction

White, IN: 37 requests in the PJM queue, 13 active totaling 770.3 MW.

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-14 Status change n/a Engineering and Procurement → Under Construction

Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy200
MW capacity120
MFO200

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first