Jewett Energy Center 1 Gas
ERCOT queue ID 29INR0150
Jewett Energy Center 1 Gas (29INR0150) is listed in the ERCOT interconnection queue as a 1,274 MW gas project in Freestone County, TX. The filing names Tap # JEWETT_N5 - # LMEST_POI_5 and Tap # JEWETT_S5 - # LMEST_POI_5 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of November 1, 2029. It records the screening study as complete on November 19, 2025 and the interconnection agreement as signed on July 15, 2026.
| Queue ID | 29INR0150 |
|---|---|
| Project name | Jewett Energy Center 1 Gas |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap # JEWETT_N5 - # LMEST_POI_5 and Tap # JEWETT_S5 - # LMEST_POI_5 |
| Point of interconnection | Tap #3391 JEWETT_N5 - #46020 LMEST_POI_5 and Tap #3390 JEWETT_S5 - #46020 LMEST_POI_5 |
| County | Freestone |
| State | TX |
| Voltage | Not reported |
| Capacity | 1,274 MW |
| Resource (as published) | GAS/CC |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2029-11-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Freestone, TX: 24 requests in the ERCOT queue, 24 active totaling 7,337.8 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-09-07 | Status change | n/a | SS Completed, FIS Started, No IA → SS Completed, FIS Started, IA |
Additional filed fields
| Interconnecting entity | Jewett Energy Center LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | GAS |
| Technology code | CC |
| Interconnection agreement signed | 2026-07-15 |
| Screening study complete | 2025-11-19 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.