Brazos Energy Security

ERCOT queue ID 28INR0456

Queue ID28INR0456
Project nameBrazos Energy Security
Status (as published)SS Completed, FIS Started, No IA
SubstationTap (Bus #) Tonkawa Switch – (Bus #) Dusty Road
Point of interconnectionTap 345 kV (Bus #1048) Tonkawa Switch – (Bus #11050) Dusty Road
CountyFisher
StateTX
Voltage345 kV
Capacity3,000 MW
Resource (as published)GAS/CC
Resource categoryGas (normalised for filtering)
Target commercial operation2030-09-22
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 New request 3,000 Not reported → SS Completed, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting EntityGolden Spread Electric
Cdr ZoneWEST
Fuel CodeGAS
Technology CodeCC
Screening Study Complete46028