Vast Sands Power II (TEF-Due Diligence)

ERCOT queue ID 28INR0109

Vast Sands Power II (TEF-Due Diligence) (28INR0109) is listed in the ERCOT interconnection queue as a 440 MW gas project in Ward County, TX. The filing names Tap Wolf Switch - Quarry Field Switch Ckt 2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of June 30, 2028. It records the screening study as complete on October 8, 2024, the full interconnection study as approved on September 16, 2026 and the interconnection agreement as signed on October 31, 2025.

Queue ID28INR0109
Project nameVast Sands Power II (TEF-Due Diligence)
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Wolf Switch - Quarry Field Switch Ckt 2
Point of interconnectionTap 345kV 11010 Wolf Switch - 11188 Quarry Field Switch Ckt 2
CountyWard
StateTX
Voltage345 kV
Capacity440 MW
Resource (as published)GAS/GT
Resource categoryGas (normalized for filtering)
Target commercial operation2028-06-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Wolf Switch - Quarry Field Switch Ckt 2 substation: 2 requests in the ERCOT queue, 2 active totaling 880 MW.

Queue IDProjectMWResourceStatus
28INR0105Vast Sands Power I (TEF -Due Diligence)440GasSS Completed, FIS Completed, IA

Ward, TX: 13 requests in the ERCOT queue, 12 active totaling 3,247.7 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting entityPermian Power I LLC
CDR reporting zoneWEST
Fuel codeGAS
Technology codeGT
Interconnection agreement signed2025-10-31
Screening study complete2024-10-08
Full interconnection study approved2026-09-16
Air permit2026-01-12
Water availability2026-04-12

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.