Sweetwater 5 Repower
ERCOT queue ID 28INR0504
Sweetwater 5 Repower (28INR0504) is listed in the ERCOT interconnection queue as a 79.1 MW wind project in Nolan County, TX. The filing names Bitter Creek Substation as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of February 1, 2029. It records the screening study as complete on July 8, 2026.
| Queue ID | 28INR0504 |
|---|---|
| Project name | Sweetwater 5 Repower |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Bitter Creek Substation |
| Point of interconnection | Bitter Creek Substation |
| County | Nolan |
| State | TX |
| Voltage | Not reported |
| Capacity | 79.1 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2029-02-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Nolan, TX: 18 requests in the ERCOT queue, 18 active totaling 4,440.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Sweetwater Wind 5 LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | WIN |
| Technology code | WT |
| Screening study complete | 2026-07-08 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.