| Queue ID | 27INR0500 |
|---|---|
| Project name | Antila Solar |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | # Buck Canyon |
| Point of interconnection | #59916 Buck Canyon 345kV |
| County | Borden |
| State | TX |
| Voltage | 345 kV |
| Capacity | 500 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2027-11-30 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Antila Solar LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 45882 |
| Screening Study Complete | 45857 |
| Water Availability | Not Required |