PARKWAY GENERATION OPERATING LLC (AH1-744) is listed in the PJM interconnection queue as a 48.3 MW gas project in Prince George's County, MD. The filing names Cheltenham as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of November 22, 2027.

Queue IDAH1-744
Project namePARKWAY GENERATION OPERATING LLC
Status (as published)EP
SubstationCheltenham
Point of interconnectionCheltenham 500 kV
CountyPrince George's
StateMD
Voltage500 kV
Capacity48.3 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2027-11-22
Source datasetcycle

Same substation and county

Cheltenham substation: 4 requests in the PJM queue, 4 active totaling 1,266.3 MW.

Queue IDProjectMWResourceStatus
C01-1494Cheltenham 500 kV618GasActive
C01-1268Cheltenham 500 kV400BatteryActive
C01-1132Cheltenham 500 kV200BatteryActive

Prince George's, MD: 57 requests in the PJM queue, 14 active totaling 3,551.2 MW.

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Status change n/a Active → EP

Full change log →

Additional filed fields

DeveloperParkway Generation Operating, LLC
Transmission ownerPEPCO
Project typeGeneration Interconnection
CycleTC2
StageFinal Agreement
MW energy53.5
MW capacity48.285
MFO853.5
Submitted date4/11/2025
Last updated7/22/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first