Trail Ranch Storage
ERCOT queue ID 29INR0273
Trail Ranch Storage (29INR0273) is listed in the ERCOT interconnection queue as a 240 MW battery project in Concho County, TX. The filing names Tap Red Creek - Amos Creek as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 1, 2030. It records the screening study as complete on March 25, 2026.
| Queue ID | 29INR0273 |
|---|---|
| Project name | Trail Ranch Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Red Creek - Amos Creek |
| Point of interconnection | Tap 345 kV 6444 Red Creek -7077 Amos Creek |
| County | Concho |
| State | TX |
| Voltage | 345 kV |
| Capacity | 240 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2030-12-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap Red Creek - Amos Creek substation: 2 requests in the ERCOT queue, 2 active totaling 372.9 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 29INR0272 | Trail Ranch Solar 2 | 132.9 | Solar | SS Completed, FIS Started, No IA |
Concho, TX: 11 requests in the ERCOT queue, 10 active totaling 2,896 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-11-09 | New request | 240 | Not reported → SS Completed, FIS Started, No IA |
Additional filed fields
| Interconnecting entity | Aurora Solar LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2026-03-25 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.