Echols Grove Solar

ERCOT queue ID 25INR0368

Echols Grove Solar (25INR0368) is listed in the ERCOT interconnection queue as a 201 MW solar project in Lamar County, TX. The filing names Tap Hawk Hollow Switch (#) and Lamar Blossom Switch (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of June 30, 2027. It records the screening study as complete on July 5, 2023, the full interconnection study as approved on June 18, 2026 and the interconnection agreement as signed on July 6, 2024.

Queue ID25INR0368
Project nameEchols Grove Solar
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Hawk Hollow Switch (#) and Lamar Blossom Switch (#)
Point of interconnectionTap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770)
CountyLamar
StateTX
Voltage138 kV
Capacity201 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-06-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-11-09 Capacity revised −0.6 SS Completed, FIS Completed, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting entityEchols Grove, LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2024-07-06
Screening study complete2023-07-05
Full interconnection study approved2026-06-18
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.