| Project | Zone | State | Cost estimate | In service | Status |
|---|---|---|---|---|---|
| Valley Link | AEP, APS/FE, DVP | WV, VA, MD (state affiliate VLT-MD) | $5,115M (2026 dollars) | 5/31/2031 | Selected, 2024 Open Window #1 |
| Dominion 2025 Window 1 Portfolio (2025-W1-275) | Dominion | VA (Chesterfield and Dinwiddie County, for the Carson - Midlothian rebuild) | $4,832.45M | 6/1/2032 | Recommended Solution |
| Ohio Seven Year Solution (765 kV) | AEP/ATSI/DAYTON/DEOK | $2,768.0M | Listed per component | Recommended (2nd read) | |
| Kammer - Juniata 765 kV | AEP, APS, PENELEC, PPL | $1,789.39M | 6/1/2032 | Approved | |
| Brandon Shores deactivation upgrades | BGE | $1,513.96 million | 12/31/2028 | Previously approved; cost changes reported | |
| 2022 Window 3 Northern Virginia/Doubs Cluster | Dominion, APS, PEPCO | $1,418.3M | 6/1/2028 | Recommended (baseline) | |
| 2022 Window 3 South Cluster | Dominion | $1,265.85M | 6/1/2028 | Recommended (baseline) | |
| ComEd MISO Tranche 2.1 | ComEd | Illinois | $908.7M | 6/1/2034 | Conceptual |
| MidAtlantic Resiliency Link (MARL) | APS | VA (Frederick County, Woodside substation), PA, WV, MD | $844.80M | December 2028 (Woodside substation) | State applications, January 2026 |
| Bramah–High Ridge 500 kV | BGE, PECO, PEPCO, DPL | $708.77M | 2028-2030 | Cost update | |
| Dominion 230 kV Reinforcements (2024-W1-24) | Dominion | VA (South Hill, Virginia, for the Raines - Cloud line) | $672.43M | 6/1/2029 | Recommended Solution |
| North Anna - Thornburg - Bristers 500kV Line | Dominion | $661.63M | 9/16/2030 | Approved baseline | |
| Northwest Ohio 345kV | AEP | OH | $607.548 M | 09/26/2031 | Scoping |
| Piqua data center service (Dayton-2025-007) | Dayton | OH | $591.5M | June 30, 2032 | Conceptual |
| Champlain Substation | PEPCO | DC | $590M | 7/1/2029 | Engineering |
| Jeffersonville, Wilmington | Dayton | OH | $589.8M | 01/2031 | Engineering |
| EKPC Mason County, KY | EKPC | KY | $566.35M | 9/01/2028 | Engineering |
| MAAC PPL Cluster | PPL | $565.4M | 6/1/2030 | Recommended Read | |
| Tanners Creek - Hanna 345 kV | AEP | IN | $520 M | 10/15/2031 | Scoping |
| Tamarack Substation | PPL | PA (Gouldsboro, PA is printed for the same customer's earlier request, PPL-2025-0012) | $486 M | 05/30/2031 | Project Development |
| ComEd 345kV STATCOMs | ComEd | $472.0M | 06/01/2031 | Conceptual | |
| Olive - Reynolds 345kV | AEP | $452.64 M | 05/30/2031 | Local Plan submission | |
| Maryland Piedmont Reliability Project (MPRP): Chanceford - Doubs 500 kV | PPL, BGE | PA, MD | $447.5M (PSEG) | 6/1/2027 | Approved |
| Mars–Golden | Dominion | $431.62M | 6/1/2027 | Baseline; revised solution | |
| Razzler Customer Delivery | AEP | OH | $416.94 M | 11/07/2028 | Scoping |
| Natalie Substation | PPL | PA | $408 M | 12/30/2029 | Project Development |
| 2022 Window 3 West Cluster Incumbent Upgrades | FE, Dominion, AEP | $392.55M | 6/1/2027 – 6/1/2030 | Recommended (baseline) | |
| AEP Central/NW Ohio, Indiana portfolio | AEP | OH, IN | $378.3M | 10/13/2027 | Scoping |
| Sammis – Star 345 kV | ATSI | $343.70M | 5/30/2031 | Conceptual | |
| Venator Station | AEP | KY | $324.2 M | 10/22/2028 | Scoping |
| Customer in Elk Grove (ComEd-2024-003) | ComEd | $319.4M | 12/31/2027, 12/31/2028 | Engineering | |
| Exelon/PEPCO Cluster | PEPCO | $282.16M | 6/1/2032 | Recommended Solution | |
| Customer in Joliet (ComEd-2025-016) | ComEd | $269M | 7/1/2028 | Conceptual | |
| Zeus 230kV Delivery | Dominion | VA | $256M | Q4 2030 | Engineering |
| Customer in Grayslake (ComEd-2025-005) | ComEd | $248.8M | 6/1/2027 to 6/1/2031 | Conceptual | |
| Patina 765/345 kV, Marysville (Dayton-2025-008) | Dayton | OH | $246M | 05/01/2031 | Conceptual |
| Bernheisel Substation | PPL | PA | $244M | 6/30/2026; 6/1/2027 | Conceptual |
| New Buffalo | PPL | PA | $242 M | 05/30/2028 | Conceptual |
| Gordon Switchyard | PPL | PA | $231.65 M | 05/30/2028 | Conceptual |
| Project Avalon | AEP | WV | $224.906 M | 09/01/2029 | Scoping |
| Archbald Mountain | PPL | PA | $220 M | 05/30/2028 | Project Development |
| ATSI Cluster 2 | ATSI | Ohio | $217.32M | 6/1/2029 | Second Read |
| 500kV Line #579 Rebuild (Septa - Yadkin) | Dominion | $216.78 M | 6/1/2029 | Second Review | |
| Customer in Dekalb (ComEd-2024-001) | ComEd | $215M | 12/31/27 | Engineering | |
| Harwood (Tomhicken switchyard) | PPL | PA | $195.55 M | 06/01/2027 | Conceptual |
| Orefield Substation | PPL | PA | $194 M | 05/31/2028 | Conceptual |
| Big Bass 230kV Switchyard | PPL | PA | $186.875 M | 05/30/2028 | Conceptual |
| Project Amazing Sites 100 and 201 | AEP | IN | $184.977M | 12/15/2026 | Scoping |
| Pike, Mingo, McDowell & Buchanan 69kV | AEP | KY, WV, VA | $182.56M | 6/1/2030 | Scoping |
| Fredericksburg to Possum Corridor 230kV Lines | Dominion | $180.0M | 06/01/2029 | Conceptual | |
| Mendota-Sandwich 138 kV | ComEd | $171.88 M | 4/15/2030 | Recommended | |
| Thelma - Big Sandy - Busseyville 138 kV | AEP | KY | $169.555 M | 11/01/2030 | Scoping |
| New Haven, Indiana | AEP | Indiana | $169.1 M | 07/01/2029 | Scoping |
Each record groups PJM planning rows that the cited quote shows are one program. Quotes are checked against the archived PDF text. Costs and dates are the documents' estimates as printed. History rows are machine-extracted and shown only where the value passed the PDF text check. News links are third-party coverage, listed for reference. Substation Scout does not verify their claims.