Large, named transmission projects in PJM planning materials: what each includes, what it is estimated to cost, and how that changed from meeting to meeting.

These are utility and PJM projects, not generation interconnection requests. Each page is built from a hand-checked record that ties the PJM planning rows of one project together, with every figure linked to its page.

ProjectZoneStateCost estimateIn serviceStatus
Valley LinkAEP, APS/FE, DVPWV, VA, MD (state affiliate VLT-MD)$5,115M (2026 dollars)5/31/2031Selected, 2024 Open Window #1
Dominion 2025 Window 1 Portfolio (2025-W1-275)DominionVA (Chesterfield and Dinwiddie County, for the Carson - Midlothian rebuild)$4,832.45M6/1/2032Recommended Solution
Ohio Seven Year Solution (765 kV)AEP/ATSI/DAYTON/DEOK$2,768.0MListed per componentRecommended (2nd read)
Kammer - Juniata 765 kVAEP, APS, PENELEC, PPL$1,789.39M6/1/2032Approved
Brandon Shores deactivation upgradesBGE$1,513.96 million12/31/2028Previously approved; cost changes reported
2022 Window 3 Northern Virginia/Doubs ClusterDominion, APS, PEPCO$1,418.3M6/1/2028Recommended (baseline)
2022 Window 3 South ClusterDominion$1,265.85M6/1/2028Recommended (baseline)
ComEd MISO Tranche 2.1ComEdIllinois$908.7M6/1/2034Conceptual
MidAtlantic Resiliency Link (MARL)APSVA (Frederick County, Woodside substation), PA, WV, MD$844.80MDecember 2028 (Woodside substation)State applications, January 2026
Bramah–High Ridge 500 kVBGE, PECO, PEPCO, DPL$708.77M2028-2030Cost update
Dominion 230 kV Reinforcements (2024-W1-24)DominionVA (South Hill, Virginia, for the Raines - Cloud line)$672.43M6/1/2029Recommended Solution
North Anna - Thornburg - Bristers 500kV LineDominion$661.63M9/16/2030Approved baseline
Northwest Ohio 345kVAEPOH$607.548 M09/26/2031Scoping
Piqua data center service (Dayton-2025-007)DaytonOH$591.5MJune 30, 2032Conceptual
Champlain SubstationPEPCODC$590M7/1/2029Engineering
Jeffersonville, WilmingtonDaytonOH$589.8M01/2031Engineering
EKPC Mason County, KYEKPCKY$566.35M9/01/2028Engineering
MAAC PPL ClusterPPL$565.4M6/1/2030Recommended Read
Tanners Creek - Hanna 345 kVAEPIN$520 M10/15/2031Scoping
Tamarack SubstationPPLPA (Gouldsboro, PA is printed for the same customer's earlier request, PPL-2025-0012)$486 M05/30/2031Project Development
ComEd 345kV STATCOMsComEd$472.0M06/01/2031Conceptual
Olive - Reynolds 345kVAEP$452.64 M05/30/2031Local Plan submission
Maryland Piedmont Reliability Project (MPRP): Chanceford - Doubs 500 kVPPL, BGEPA, MD$447.5M (PSEG)6/1/2027Approved
Mars–GoldenDominion$431.62M6/1/2027Baseline; revised solution
Razzler Customer DeliveryAEPOH$416.94 M11/07/2028Scoping
Natalie SubstationPPLPA$408 M12/30/2029Project Development
2022 Window 3 West Cluster Incumbent UpgradesFE, Dominion, AEP$392.55M6/1/2027 – 6/1/2030Recommended (baseline)
AEP Central/NW Ohio, Indiana portfolioAEPOH, IN$378.3M10/13/2027Scoping
Sammis – Star 345 kVATSI$343.70M5/30/2031Conceptual
Venator StationAEPKY$324.2 M10/22/2028Scoping
Customer in Elk Grove (ComEd-2024-003)ComEd$319.4M12/31/2027, 12/31/2028Engineering
Exelon/PEPCO ClusterPEPCO$282.16M6/1/2032Recommended Solution
Customer in Joliet (ComEd-2025-016)ComEd$269M7/1/2028Conceptual
Zeus 230kV DeliveryDominionVA$256MQ4 2030Engineering
Customer in Grayslake (ComEd-2025-005)ComEd$248.8M6/1/2027 to 6/1/2031Conceptual
Patina 765/345 kV, Marysville (Dayton-2025-008)DaytonOH$246M05/01/2031Conceptual
Bernheisel SubstationPPLPA$244M6/30/2026; 6/1/2027Conceptual
New BuffaloPPLPA$242 M05/30/2028Conceptual
Gordon SwitchyardPPLPA$231.65 M05/30/2028Conceptual
Project AvalonAEPWV$224.906 M09/01/2029Scoping
Archbald MountainPPLPA$220 M05/30/2028Project Development
ATSI Cluster 2ATSIOhio$217.32M6/1/2029Second Read
500kV Line #579 Rebuild (Septa - Yadkin)Dominion$216.78 M6/1/2029Second Review
Customer in Dekalb (ComEd-2024-001)ComEd$215M12/31/27Engineering
Harwood (Tomhicken switchyard)PPLPA$195.55 M06/01/2027Conceptual
Orefield SubstationPPLPA$194 M05/31/2028Conceptual
Big Bass 230kV SwitchyardPPLPA$186.875 M05/30/2028Conceptual
Project Amazing Sites 100 and 201AEPIN$184.977M12/15/2026Scoping
Pike, Mingo, McDowell & Buchanan 69kVAEPKY, WV, VA$182.56M6/1/2030Scoping
Fredericksburg to Possum Corridor 230kV LinesDominion$180.0M06/01/2029Conceptual
Mendota-Sandwich 138 kVComEd$171.88 M4/15/2030Recommended
Thelma - Big Sandy - Busseyville 138 kVAEPKY$169.555 M11/01/2030Scoping
New Haven, IndianaAEPIndiana$169.1 M07/01/2029Scoping

Each record groups PJM planning rows that the cited quote shows are one program. Quotes are checked against the archived PDF text. Costs and dates are the documents' estimates as printed. History rows are machine-extracted and shown only where the value passed the PDF text check. News links are third-party coverage, listed for reference. Substation Scout does not verify their claims.