Not reported
BPA queue ID G0617
| Queue ID | G0617 |
|---|---|
| Project name | Not reported |
| Status (as published) | STUDY COMPLETED |
| Substation | John Day No 2 transmission line or Biglow Canyon Substation. |
| Point of interconnection | John Day No 2 230 kV transmission line or Biglow Canyon Substation. |
| County | Sherman |
| State | OR |
| Voltage | 230 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Solar/Photovoltaic |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2022-08-01 |
| Source dataset | bpa-generation |
Tracked changes
2 changes observed between weekly snapshots of the BPA queue since BPA tracking began on September 22, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-12 | Capacity revised | −200 | STUDY COMPLETED → STUDY COMPLETED |
| 2026-10-05 | Status change | n/a | STUDY → STUDY COMPLETED |
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS & ERIS |
| Poi | John Day No 2 230 kV transmission line or Biglow Canyon Substation. |
| Generator Type | Photovoltaic |
| Fuel Source | Solar |
| Nameplate Mw Total | 300 |
| Max Summer Mw | 0 |
| Max Winter Mw | 0 |
| Reason Not Completed | . |
| Comments | 200 MW solar facility with a 100/4hr battery, generating a max of 200 MW at POI combined with Golden Hills Wind (G0099 - part 2). |