Brahman Renewables Storage
ERCOT queue ID 29INR0059
Brahman Renewables Storage (29INR0059) is listed in the ERCOT interconnection queue as a 206.9 MW battery project in Milam County, TX. The filing names Tap Voss Lake switch # – Badger Switch # as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of May 1, 2029. It records the screening study as complete on January 25, 2025.
| Queue ID | 29INR0059 |
|---|---|
| Project name | Brahman Renewables Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Voss Lake switch # – Badger Switch # |
| Point of interconnection | Tap Voss Lake switch #3751 – Badger Switch #3761 345 kV |
| County | Milam |
| State | TX |
| Voltage | 345 kV |
| Capacity | 206.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-05-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap Voss Lake switch # – Badger Switch # substation: 2 requests in the ERCOT queue, 2 active totaling 307.5 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 29INR0058 | Brahman Renewables Solar | 100.6 | Solar | SS Completed, FIS Started, No IA |
Milam, TX: 35 requests in the ERCOT queue, 30 active totaling 8,525.6 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Capacity revised | +3.8 | SS Completed, FIS Started, No IA → SS Completed, FIS Started, No IA |
Additional filed fields
| Interconnecting entity | Brahman Renewables |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2025-01-25 |