Substation Scout

Blue Energy Center - Phase 3 – Steam Stage 2

ERCOT queue ID 33INR0007

Queue ID33INR0007
Project nameBlue Energy Center - Phase 3 – Steam Stage 2
Status (as published)SS Started, FIS Started, No IA
SubstationTap DULCE7A - STATIC7A
Point of interconnectionTap 345kV 80286 DULCE7A - 8676 STATIC7A
CountyVictoria
StateTX
Voltage345 kV
Capacity1,320 MW
Resource (as published)NUC/ST
Resource categoryNuclear (normalised for filtering)
Target commercial operation2033-06-15
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 New request 1,320 Not reported → SS Started, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting EntitySister 1, LLC
Cdr ZoneSOUTH
Fuel CodeNUC
Technology CodeST

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.