Not reported

BPA queue ID G1003

Queue IDG1003
Project nameNot reported
Status (as published)STUDY COMPLETED
SubstationHatton tap to Connell tap to Benton-Scooteney No 1 line
Point of interconnectionHatton tap to Connell tap to Benton-Scooteney No 1 115kV line
CountyAdams
StateWA
Voltage115 kV
Capacity3 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-31
Source datasetbpa-generation

Tracked changes

1 change observed between weekly snapshots of the BPA queue since BPA tracking began on September 22, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a STUDY → STUDY COMPLETED

Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiHatton tap to Connell tap to Benton-Scooteney No 1 115kV line
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total3
Max Summer Mw3
Max Winter Mw3
Reason Not Completed.