TempleCloud Gas (28INR0508) is listed in the ERCOT interconnection queue as a 1,139.7 MW gas project in Bell County, TX. The filing names Tap # Temple Switch - # Tower Switch DCKT Line as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of October 19, 2029. It records the screening study as complete on October 21, 2026.

Queue ID28INR0508
Project nameTempleCloud Gas
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # Temple Switch - # Tower Switch DCKT Line
Point of interconnectionTap #3414 Temple Switch - #3780 Tower Switch 345kV DCKT Line
CountyBell
StateTX
Voltage345 kV
Capacity1,139.7 MW
Resource (as published)GAS/IC
Resource categoryGas (normalized for filtering)
Target commercial operation2029-10-19
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap # Temple Switch - # Tower Switch DCKT Line substation: 2 requests in the ERCOT queue, 2 active totaling 1,776.6 MW.

Queue IDProjectMWResourceStatus
29INR0206Riviera Gas636.9GasSS Completed, FIS Started, No IA

Bell, TX: 14 requests in the ERCOT queue, 14 active totaling 4,237.3 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-11-09 New request 1,139.7 Not reported → SS Completed, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting entityKalnin Ventures, LLC
CDR reporting zoneNORTH
Fuel codeGAS
Technology codeIC
Screening study complete2026-10-21

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first