Substation Scout

Esky Solar Project

PJM queue ID AG1-499

Esky Solar Project (AG1-499) is listed in the PJM interconnection queue as a 6 MW solar project in Gloucester County, NJ. The filing names Lambs as its point of interconnection. PJM lists its status as “Partially in Service - Under Construction”, with a target commercial operation date of August 31, 2026.

Queue IDAG1-499
Project nameEsky Solar Project
Status (as published)Partially in Service - Under Construction
SubstationLambs
Point of interconnectionLambs 12.47 kV
CountyGloucester
StateNJ
Voltage12.5 kV
Capacity6 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2026-08-31
Source datasetserial

Same substation and county

Gloucester, NJ: 88 requests in the PJM queue, 22 active totaling 1,788.6 MW.

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a Under Construction → Partially in Service - Under Construction

Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy10
MW capacity6
MFO10

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.