Substation Scout

Huisache Solar

ERCOT queue ID 24INR0160

Huisache Solar (24INR0160) is listed in the ERCOT interconnection queue as a 125.6 MW solar project in Wilson County, TX. The filing names Tapping the Elm Creek to Shaula circuit 1 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of June 30, 2029. It records the screening study as complete on March 1, 2022, the full interconnection study as approved on September 23, 2025 and the interconnection agreement as signed on August 12, 2025.

Queue ID24INR0160
Project nameHuisache Solar
Status (as published)SS Completed, FIS Completed, IA
SubstationTapping the Elm Creek to Shaula circuit 1
Point of interconnectionTapping the Elm Creek to Shaula circuit 1
CountyWilson
StateTX
VoltageNot reported
Capacity125.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2029-06-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tapping the Elm Creek to Shaula circuit 1 substation: 2 requests in the ERCOT queue, 2 active totaling 226.3 MW.

Queue IDProjectMWResourceStatus
24INR0376Huisache BESS100.7BatterySS Completed, FIS Completed, IA

Wilson, TX: 18 requests in the ERCOT queue, 15 active totaling 3,532.8 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-11-09 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting entityHuisache Solar, LLC
CDR reporting zoneSOUTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2025-08-12
Screening study complete2022-03-01
Full interconnection study approved2025-09-23
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first