Huisache Solar
ERCOT queue ID 24INR0160
Huisache Solar (24INR0160) is listed in the ERCOT interconnection queue as a 125.6 MW solar project in Wilson County, TX. The filing names Tapping the Elm Creek to Shaula circuit 1 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of June 30, 2029. It records the screening study as complete on March 1, 2022, the full interconnection study as approved on September 23, 2025 and the interconnection agreement as signed on August 12, 2025.
| Queue ID | 24INR0160 |
|---|---|
| Project name | Huisache Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tapping the Elm Creek to Shaula circuit 1 |
| Point of interconnection | Tapping the Elm Creek to Shaula circuit 1 |
| County | Wilson |
| State | TX |
| Voltage | Not reported |
| Capacity | 125.6 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2029-06-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tapping the Elm Creek to Shaula circuit 1 substation: 2 requests in the ERCOT queue, 2 active totaling 226.3 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 24INR0376 | Huisache BESS | 100.7 | Battery | SS Completed, FIS Completed, IA |
Wilson, TX: 18 requests in the ERCOT queue, 15 active totaling 3,532.8 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-11-09 | Status change | n/a | SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA |
Additional filed fields
| Interconnecting entity | Huisache Solar, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2025-08-12 |
| Screening study complete | 2022-03-01 |
| Full interconnection study approved | 2025-09-23 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.