| Queue ID | 16INR0112 |
|---|---|
| Project name | Loma Pinta Wind |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Fowlerton |
| Point of interconnection | 5705 Fowlerton 138kV |
| County | La Salle |
| State | TX |
| Voltage | 138 kV |
| Capacity | 197 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2026-12-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Enerverse |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | WIN |
| Technology Code | WT |
| Ia Signed | 43082 |
| Screening Study Complete | 42187 |
| Air Permit | Not Required |
| Water Availability | Not Required |