Blackford Wind Energy Project
PJM queue ID AF1-202
Blackford Wind Energy Project (AF1-202) is listed in the PJM interconnection queue as a 34 MW wind project in Blackford County, IN. The filing names Keystone-Desoto as its point of interconnection. PJM lists its status as “Partially in Service - Under Construction”, with a target commercial operation date of September 15, 2026.
| Queue ID | AF1-202 |
|---|---|
| Project name | Blackford Wind Energy Project |
| Status (as published) | Partially in Service - Under Construction |
| Substation | Keystone-Desoto |
| Point of interconnection | Keystone-Desoto 345 kV |
| County | Blackford |
| State | IN |
| Voltage | 345 kV |
| Capacity | 34 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2026-09-15 |
| Source dataset | serial |
Same substation and county
Keystone-Desoto substation: 7 requests in the PJM queue, 5 active totaling 329.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF1-119 | Lake Trout Solar | 140 | Hybrid | Engineering and Procurement |
| AF1-223 | Blackford Solar Energy Project | 90 | Solar | Partially in Service - Under Construction |
| AF2-388 | Prairie Creek Wind | 35.2 | Wind | EP |
| AF2-162 | Lake Trout Solar | 30 | Solar | Engineering and Procurement |
| AI2-489 | Keystone-Desoto 345 kV | 97.2 | Wind | Withdrawn |
| AI2-394 | Keystone-Desoto 345 kV | 66 | Wind | Withdrawn |
Blackford, IN: 18 requests in the PJM queue, 10 active totaling 547.4 MW.
Tracked changes
1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-11-16 | Status change | n/a | Under Construction → Partially in Service - Under Construction |
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 200 |
| MW capacity | 34 |
| MFO | 200 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.