Substation Scout

Skeeter Solar

ERCOT queue ID 29INR0026

Queue ID29INR0026
Project nameSkeeter Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationSWEETWATER EAST () - LONG CREEK ()
Point of interconnection345 kV SWEETWATER EAST (11420) - LONG CREEK (1435)
CountyJones
StateTX
Voltage345 kV
Capacity251 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-06-30
Source datasetlarge

Additional filed fields

Interconnecting EntityMesquite Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45533
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.