Substation Scout

Starling Solar

ERCOT queue ID 24INR0440

Queue ID24INR0440
Project nameStarling Solar
Status (as published)SS Completed, FIS Started, IA
Substation138-kV Birdhouse () Starling Solar Phase II is a an addition of 42.24MW to the 23INR0035 (solar) filed in . 23INR0181 (storage) was filed in .
Point of interconnection138-kV Birdhouse (7255) Starling Solar Phase II is a an addition of 42.24MW to the 23INR0035 (solar) filed in 2020. 23INR0181 (storage) was filed in 2021.
CountyGonzales
StateTX
VoltageNot reported
Capacity140.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-01-28
Source datasetlarge

Additional filed fields

Interconnecting EntityStarling Solar, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Ia Signed46070
Screening Study Complete44923
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.