Substation Scout

Starling Solar

ERCOT queue ID 24INR0440

Starling Solar (24INR0440) is listed in the ERCOT interconnection queue as a 144.6 MW solar project in Gonzales County, TX. The filing names 138-kV Birdhouse Starling Solar Phase II is a an addition of 42.24MW to the 23INR0035 (solar) filed in . 23INR0181 (storage) was filed in . as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of January 28, 2028. It records the screening study as complete on December 28, 2022 and the interconnection agreement as signed on February 17, 2026.

Queue ID24INR0440
Project nameStarling Solar
Status (as published)SS Completed, FIS Started, IA
Substation138-kV Birdhouse Starling Solar Phase II is a an addition of 42.24MW to the 23INR0035 (solar) filed in . 23INR0181 (storage) was filed in .
Point of interconnection138-kV Birdhouse (7255) Starling Solar Phase II is a an addition of 42.24MW to the 23INR0035 (solar) filed in 2020. 23INR0181 (storage) was filed in 2021.
CountyGonzales
StateTX
VoltageNot reported
Capacity144.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-01-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Gonzales, TX: 8 requests in the ERCOT queue, 7 active totaling 1,171.9 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Capacity revised +4 SS Completed, FIS Started, IA → SS Completed, FIS Started, IA

Full change log →

Additional filed fields

Interconnecting entityStarling Solar, LLC
CDR reporting zoneSOUTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2026-02-17
Screening study complete2022-12-28
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.