Trumpet Solar

ERCOT queue ID 29INR0360

Queue ID29INR0360
Project nameTrumpet Solar
Status (as published)SS Completed, FIS Started, No IA
Substationtap Drylake_5 – TNFaulkner3
Point of interconnectiontap 345kV 18723 Drylake_5 – 38125 TNFaulkner3
CountyReeves
StateTX
Voltage345 kV
Capacity533 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-07-01
Source datasetlarge

Tracked changes

2 changes observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Capacity revised +78 SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA
2026-10-05 Status change n/a SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting EntityNextEra Energy Resources Interconnection Holdings LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete46276
Water AvailabilityNot Required