Substation Scout

Bob Creek Wind

ERCOT queue ID 27INR0076

Queue ID27INR0076
Project nameBob Creek Wind
Status (as published)SS Completed, FIS Started, IA
SubstationSand Bluff
Point of interconnection59902 Sand Bluff 345kV
CountySterling
StateTX
Voltage345 kV
Capacity240 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2028-07-01
Source datasetlarge

Additional filed fields

Interconnecting EntityNextEra Energy Interconnection Holdings, LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Ia Signed45814
Screening Study Complete45390
Air PermitNot Required
Water AvailabilityNot Required