Substation Scout

Not reported

BPA queue ID G0796 Terminal status

Queue IDG0796
Project nameNot reported
Status (as published)WITHDRAWN
SubstationBPA John Day-Big Eddy 1/2 transmission lines.
Point of interconnectionBPA 500 KV John Day-Big Eddy 1/2 transmission lines.
CountySherman
StateOR
Voltage500 kV
Capacity650 MW
Resource (as published)Battery/Energy Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-01-02
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiBPA 500 KV John Day-Big Eddy 1/2 transmission lines.
Generator TypeEnergy Storage
Fuel SourceBattery
Nameplate Mw Total661.3
Max Summer Mw650
Max Winter Mw650
ClusterTransition Cluster
Reason Not Completed.
Commentsgrid-charging

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.