Bronc Rodeo Solar Project
ERCOT queue ID 25INR0440
| Queue ID | 25INR0440 |
|---|---|
| Project name | Bronc Rodeo Solar Project |
| Status (as published) | SS Completed, FIS Completed, No IA |
| Substation | Tap Line from Temple Pecan Creek (#) to the Cow Bayou Switch (#) |
| Point of interconnection | Tap 138 kV Line from Temple Pecan Creek (#3420) to the Cow Bayou Switch (#3385) |
| County | Falls |
| State | TX |
| Voltage | 138 kV |
| Capacity | 105.7 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-09-18 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Energiekontor US Texas SP 16 LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 45135 |
| Fis Approved | 45741 |
| Air Permit | Not Required |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.