Substation Scout

Helion Solar

ERCOT queue ID 27INR0623

Queue ID27INR0623
Project nameHelion Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationGALVANI 345
Point of interconnection59912 GALVANI 345
CountyScurry
StateTX
VoltageNot reported
Capacity100 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2027-10-22
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Status change n/a SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting EntityHelion Solar LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete46246
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.