Mammoth Central II Energy Center (AG1-302) is listed in the PJM interconnection queue as a 180 MW solar project in Pulaski County, IN. The filing names Olive-Reynolds #1 as its point of interconnection. PJM lists its status as “Partially in Service - Under Construction”, with a target commercial operation date of January 15, 2028.

Queue IDAG1-302
Project nameMammoth Central II Energy Center
Status (as published)Partially in Service - Under Construction
SubstationOlive-Reynolds #1
Point of interconnectionOlive-Reynolds #1 345 kV
CountyPulaski
StateIN
Voltage345 kV
Capacity180 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-01-15
Source datasetserial

Same substation and county

Olive-Reynolds #1 substation: 3 requests in the PJM queue, 1 active totaling 180 MW.

Queue IDProjectMWResourceStatus
AI2-401Olive-Reynolds #1 345 kV48HybridWithdrawn
AD2-138Olive-Reynolds #1 345kV35.2WindWithdrawn

Pulaski, IN: 21 requests in the PJM queue, 11 active totaling 1,270.9 MW.

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-19 Status change n/a Under Construction → Partially in Service - Under Construction

Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy300
MW capacity180
MFO300

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first