Sycamore Cross Solar

PJM queue ID AC2-141

Sycamore Cross Solar (AC2-141) is listed in the PJM interconnection queue as a 168.2 MW solar project in Isle of Wight County, VA. The filing names Septa as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of April 1, 2026.

Queue IDAC2-141
Project nameSycamore Cross Solar
Status (as published)Under Construction
SubstationSepta
Point of interconnectionSepta 500kV
CountyIsle of Wight
StateVA
Voltage500 kV
Capacity168.2 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2026-04-01
Source datasetserial

Same substation and county

Septa substation: 4 requests in the PJM queue, 2 active totaling 336.4 MW.

Queue IDProjectMWResourceStatus
AC1-161Cavalier168.2SolarIn Service
AI1-017Septa 500 kV300BatteryWithdrawn
C01-1372Septa 500 kV200BatteryWithdrawn

Isle of Wight, VA: 25 requests in the PJM queue, 9 active totaling 444.9 MW.

A substation with the same name is named in PJM transmission planning materials: Septa (DOM, 4 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-19 Status change n/a Engineering and Procurement → Under Construction

Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy240
MW capacity168.2
MFO240

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.