ERCOT queue ID 26INR0228
Santa Monica Solar (26INR0228) is listed in the ERCOT interconnection queue as a 105.9 MW solar project in Navarro County, TX. The filing names Tap NAVARRO - BIGBRNW_5 Ckt 2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of September 20, 2028. It records the screening study as complete on December 4, 2023 and the full interconnection study as approved on August 12, 2026.
| Queue ID | 26INR0228 |
|---|---|
| Project name | Santa Monica Solar |
| Status (as published) | SS Completed, FIS Completed, No IA |
| Substation | Tap NAVARRO - BIGBRNW_5 Ckt 2 |
| Point of interconnection | Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2 |
| County | Navarro |
| State | TX |
| Voltage | 345 kV |
| Capacity | 105.9 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-09-20 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Navarro, TX: 29 requests in the ERCOT queue, 26 active totaling 4,412.7 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-09-07 | Status change | n/a | SS Completed, FIS Started, No IA → SS Completed, FIS Completed, No IA |
Additional filed fields
| Interconnecting entity | Karol Solar IV |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2023-12-04 |
| Full interconnection study approved | 2026-08-12 |
| Water availability | Not Required |