Lynx Energy Storage_Full

ERCOT queue ID 27INR0655

Queue ID27INR0655
Project nameLynx Energy Storage_Full
Status (as published)SS Started, FIS Started, No IA
SubstationPRIMAVERA Substation
Point of interconnectionPRIMAVERA 138kV Substation
CountyNueces
StateTX
Voltage138 kV
Capacity50 MW
Resource (as published)MWH/SO
Resource categoryOther (normalised for filtering)
Target commercial operation2027-12-01
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 New request 50 Not reported → SS Started, FIS Started, No IA

Full change log →

Additional filed fields

Interconnecting EntityCorpus Battery Storage, LLC
Cdr ZoneCOASTAL
Fuel CodeMWH
Technology CodeSO

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.