South Everett Community Solar Project
BPA queue ID G0943
| Queue ID | G0943 |
|---|---|
| Project name | South Everett Community Solar Project |
| Status (as published) | ENERGIZED |
| Substation | Snohomish |
| Point of interconnection | Snohomish |
| County | Snohomish |
| State | WA |
| Voltage | Not reported |
| Capacity | 1 MW |
| Resource (as published) | Solar/Photovoltaic |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2024-09-30 |
| Source dataset | bpa-generation |
Tracked changes
1 change observed between weekly snapshots of the BPA queue since BPA tracking began on September 22, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Status change | n/a | STUDY → ENERGIZED |
Additional filed fields
| Requestor | Public Utility District No. 1 of Snohomish County |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | Snohomish |
| Generator Type | Photovoltaic |
| Fuel Source | Solar |
| Nameplate Mw Total | 1 |
| Max Summer Mw | 1 |
| Max Winter Mw | 1 |
| Reason Not Completed | . |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.