Caesar Storage

ERCOT queue ID 29INR0132

Caesar Storage (29INR0132) is listed in the ERCOT interconnection queue as a 205.5 MW battery project in Borden County, TX. The filing names Buck Canyon as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of November 26, 2029. It records the screening study as complete on October 22, 2025 and the interconnection agreement as signed on September 15, 2026.

Queue ID29INR0132
Project nameCaesar Storage
Status (as published)SS Completed, FIS Started, IA
SubstationBuck Canyon
Point of interconnection59916 Buck Canyon 345 kV
CountyBorden
StateTX
Voltage345 kV
Capacity205.5 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-11-26
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Buck Canyon substation: 2 requests in the ERCOT queue, 2 active totaling 387.1 MW.

Queue IDProjectMWResourceStatus
29INR0131Caesar Solar181.6SolarSS Completed, FIS Started, IA

Borden, TX: 19 requests in the ERCOT queue, 17 active totaling 5,556.7 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Started, No IA → SS Completed, FIS Started, IA

Full change log →

Additional filed fields

Interconnecting entityCaesar Solar, LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2026-09-15
Screening study complete2025-10-22

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.