Bayou Creek Solar
ERCOT queue ID 28INR0223
Bayou Creek Solar (28INR0223) is listed in the ERCOT interconnection queue as a 256.9 MW solar project in San Patricio County, TX. The filing names Goddard as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of September 25, 2028. It records the screening study as complete on March 24, 2025 and the interconnection agreement as signed on June 2, 2026.
| Queue ID | 28INR0223 |
|---|---|
| Project name | Bayou Creek Solar |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Goddard |
| Point of interconnection | 8606 Goddard 345kV |
| County | San Patricio |
| State | TX |
| Voltage | 345 kV |
| Capacity | 256.9 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-09-25 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Goddard substation: 3 requests in the ERCOT queue, 3 active totaling 677.7 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 29INR0227 | San Patricio Energy Center BESS | 300.8 | Battery | SS Completed, FIS Started, No IA |
| 22INR0392 | Kalina Solar | 120 | Solar | SS Completed, FIS Started, No IA |
San Patricio, TX: 28 requests in the ERCOT queue, 27 active totaling 6,857.5 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Capacity revised | +1.4 | SS Completed, FIS Started, IA → SS Completed, FIS Started, IA |
Additional filed fields
| Interconnecting entity | Bayou Creek Solar LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2026-06-02 |
| Screening study complete | 2025-03-24 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.