Spurland Solar III
ERCOT queue ID 29INR0294
| Queue ID | 29INR0294 |
|---|---|
| Project name | Spurland Solar III |
| Status (as published) | SS Started, FIS Started, No IA |
| Substation | Nova Prime Substation |
| Point of interconnection | Nova Prime Substation |
| County | Kent |
| State | TX |
| Voltage | Not reported |
| Capacity | 321.9 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2029-12-29 |
| Source dataset | large |
Tracked changes
2 changes observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Capacity revised | −1.3 | SS Started, FIS Started, No IA → SS Started, FIS Started, No IA |
| 2026-09-07 | New request | 323.2 | Not reported → SS Started, FIS Started, No IA |
Additional filed fields
| Interconnecting Entity | Spurland Solar III, LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.