Sunridge Solar

PJM queue ID AE2-029

Queue IDAE2-029
Project nameSunridge Solar
Status (as published)Partially in Service - Under Construction
SubstationGrottoes-Merck
Point of interconnectionGrottoes-Merck 115kV
CountyRockingham
StateVA
Voltage115 kV
Capacity30 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-11-01
Source datasetserial

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-14 Status change n/a Under Construction → Partially in Service - Under Construction

Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity30
Mfo50