EmberGreen
ERCOT queue ID 28INR0090
EmberGreen (28INR0090) is listed in the ERCOT interconnection queue as a 1,036 MW gas project in Wharton County, TX. The filing names Tap Caney - Hungerford as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of January 1, 2028. It records the screening study as complete on September 10, 2024, the full interconnection study as approved on April 21, 2026 and the interconnection agreement as signed on August 4, 2026.
| Queue ID | 28INR0090 |
|---|---|
| Project name | EmberGreen |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Caney - Hungerford |
| Point of interconnection | Tap 138kV 48050 Caney - 44150 Hungerford |
| County | Wharton |
| State | TX |
| Voltage | 138 kV |
| Capacity | 1,036 MW |
| Resource (as published) | GAS/GT |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2028-01-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Wharton, TX: 44 requests in the ERCOT queue, 42 active totaling 8,624.9 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-09-07 | Status change | n/a | SS Completed, FIS Completed, No IA → SS Completed, FIS Completed, IA |
Additional filed fields
| Interconnecting entity | EmberGreen Energy Center |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | GAS |
| Technology code | GT |
| Interconnection agreement signed | 2026-08-04 |
| Screening study complete | 2024-09-10 |
| Full interconnection study approved | 2026-04-21 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.