Substation Scout

Diamondback solar

ERCOT queue ID 20INR0162

Queue ID20INR0162
Project nameDiamondback solar
Status (as published)SS Completed, FIS Completed, IA
SubstationDel Sol
Point of interconnection80355 Del Sol 345kV
CountyStarr
StateTX
Voltage345 kV
Capacity200.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-04-29
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Capacity revised −3.3 SS Completed, FIS Completed, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting EntityDiamondback Solar, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Ia Signed45457
Screening Study Complete43440
Fis Approved46203
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.