Substation Scout

Star Dairy Solar

ERCOT queue ID 25INR0164

Star Dairy Solar (25INR0164) is listed in the ERCOT interconnection queue as a 115.6 MW solar project in Lamar County, TX. The filing names Tap PARIS_SW1_5 -- WOODARD_5 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of July 12, 2027. It records the screening study as complete on February 17, 2023, the full interconnection study as approved on September 16, 2026 and the interconnection agreement as signed on December 9, 2024.

Queue ID25INR0164
Project nameStar Dairy Solar
Status (as published)SS Completed, FIS Completed, IA
SubstationTap PARIS_SW1_5 -- WOODARD_5
Point of interconnectionTap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5
CountyLamar
StateTX
Voltage345 kV
Capacity115.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-07-12
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap PARIS_SW1_5 -- WOODARD_5 substation: 2 requests in the ERCOT queue, 2 active totaling 320.8 MW.

Queue IDProjectMWResourceStatus
25INR0334Star Dairy Storage205.2BatterySS Completed, FIS Completed, IA

Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Status change n/a SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA

Full change log →

Additional filed fields

Interconnecting entityStar Dairy Solar LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2024-12-09
Screening study complete2023-02-17
Full interconnection study approved2026-09-16
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.