Star Dairy Solar
ERCOT queue ID 25INR0164
Star Dairy Solar (25INR0164) is listed in the ERCOT interconnection queue as a 115.6 MW solar project in Lamar County, TX. The filing names Tap PARIS_SW1_5 -- WOODARD_5 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of July 12, 2027. It records the screening study as complete on February 17, 2023, the full interconnection study as approved on September 16, 2026 and the interconnection agreement as signed on December 9, 2024.
| Queue ID | 25INR0164 |
|---|---|
| Project name | Star Dairy Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap PARIS_SW1_5 -- WOODARD_5 |
| Point of interconnection | Tap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5 |
| County | Lamar |
| State | TX |
| Voltage | 345 kV |
| Capacity | 115.6 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-07-12 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap PARIS_SW1_5 -- WOODARD_5 substation: 2 requests in the ERCOT queue, 2 active totaling 320.8 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 25INR0334 | Star Dairy Storage | 205.2 | Battery | SS Completed, FIS Completed, IA |
Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-10-05 | Status change | n/a | SS Completed, FIS Started, IA → SS Completed, FIS Completed, IA |
Additional filed fields
| Interconnecting entity | Star Dairy Solar LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2024-12-09 |
| Screening study complete | 2023-02-17 |
| Full interconnection study approved | 2026-09-16 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.