Rocky Forge Wind

PJM queue ID AA1-038

Queue IDAA1-038
Project nameRocky Forge Wind
Status (as published)Partially in Service - Under Construction
SubstationLexington-Low Moor
Point of interconnectionLexington-Low Moor 230kV
CountyBotetourt
StateVA
Voltage230 kV
Capacity10.1 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2026-12-31
Source datasetserial

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-12 Status change n/a Under Construction → Partially in Service - Under Construction

Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy78.2
Mw Capacity10.1
Mfo78.2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.