ERCOT queue ID 26INR0311

Queue ID26INR0311
Project nameSenator Aggreko Solar
Status (as published)SS Completed, FIS Started, IA
SubstationSunglow Substation (#)
Point of interconnection138 kV Sunglow Substation (#78016)
CountyMaverick
StateTX
Voltage138 kV
Capacity258.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-03-31
Source datasetlarge

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Capacity revised +7.9 SS Completed, FIS Started, IA → SS Completed, FIS Started, IA

Full change log →

Additional filed fields

Interconnecting EntitySenator Aggreko Solar LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Ia Signed46022
Screening Study Complete45411
Water AvailabilityNot Required