Substation Scout

Silverbell Solar

ERCOT queue ID 28INR0125

Queue ID28INR0125
Project nameSilverbell Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Rivercrest SES - Deport REA
Point of interconnectionTap 138kV Rivercrest SES 1780 - Deport REA 1768
CountyRed River
StateTX
Voltage138 kV
Capacity125.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-09-30
Source datasetlarge

Additional filed fields

Interconnecting EntitySilverbell Energy Center, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45572
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.