Red Hat Solar
ERCOT queue ID 27INR0263
Red Hat Solar (27INR0263) is listed in the ERCOT interconnection queue as a 136.1 MW solar project in Lamar County, TX. The filing names Tap the line from Hawk Hollow Switch (#) to Lamar Blossom Tap (#) as its point of interconnection. ERCOT lists its status as “SS Started, FIS Started, No IA”, with a target commercial operation date of April 8, 2030.
| Queue ID | 27INR0263 |
|---|---|
| Project name | Red Hat Solar |
| Status (as published) | SS Started, FIS Started, No IA |
| Substation | Tap the line from Hawk Hollow Switch (#) to Lamar Blossom Tap (#) |
| Point of interconnection | Tap the 138 kV line from Hawk Hollow Switch (#11768) to Lamar Blossom Tap (#11770) |
| County | Lamar |
| State | TX |
| Voltage | 138 kV |
| Capacity | 136.1 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2030-04-08 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Lamar, TX: 28 requests in the ERCOT queue, 25 active totaling 6,189.8 MW.
Tracked changes
1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.
| Detected | Change | MW | Status was → now |
|---|---|---|---|
| 2026-11-09 | New request | 136.1 | Not reported → SS Started, FIS Started, No IA |
Additional filed fields
| Interconnecting entity | Red Hat Solar LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.