Big Field Solar

ERCOT queue ID 29INR0148

Queue ID29INR0148
Project nameBig Field Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap RILEY7A - EDITHCLA7B
Point of interconnectionTap 345kV 6101 RILEY7A - 60505 EDITHCLA7B
CountyWilbarger
StateTX
Voltage345 kV
Capacity506.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityBig Field Solar Energy LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45904
Water AvailabilityNot Required