Big Field Solar
ERCOT queue ID 29INR0148
Big Field Solar (29INR0148) is listed in the ERCOT interconnection queue as a 506.2 MW solar project in Foard County, TX. The filing names Tap RILEY7A - EDITHCLA7B as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2029. It records the screening study as complete on September 4, 2025.
| Queue ID | 29INR0148 |
|---|---|
| Project name | Big Field Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap RILEY7A - EDITHCLA7B |
| Point of interconnection | Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B |
| County | Foard |
| State | TX |
| Voltage | 345 kV |
| Capacity | 506.2 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2029-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap RILEY7A - EDITHCLA7B substation: 6 requests in the ERCOT queue, 6 active totaling 3,256.5 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 32INR0006 | H&C WILBARGER POWER I | 1,025.6 | Gas | SS Started, FIS Started, No IA |
| 32INR0008 | H&C WILBARGER POWER II | 1,025.6 | Gas | SS Started, FIS Started, No IA |
| 28INR0476 | Pease River Solar | 276.4 | Solar | SS Completed, FIS Started, No IA |
| 28INR0464 | Grayback Solar | 221.8 | Solar | SS Completed, FIS Started, No IA |
| 28INR0535 | Daisy Solar | 200.9 | Solar | SS Completed, FIS Started, No IA |
Foard, TX: 5 requests in the ERCOT queue, 5 active totaling 1,593.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Big Field Solar Energy LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2025-09-04 |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.